LIST OF COMPLETED WORKS WE HAVE REALIZED FOR PRIVATE SECTOR INVESTORS

NO
NAME OF ENTERPRISENAME OF WORKDATE OF COMMENCEMENTDATE OF COMPLETIONCONTRACT VALUE
1
YAPISAN ELEKTRİK ÜRETİM A.Ş. [YAPISAN Electricty Generation Inc.]154 KV. DARICA 1 HPP - GÖLKÖY SUBSTATION ETL ( ~25,2 km)03 09 200727 08 2009
1.416.849,91 TL
1.684.573,36 USD
2
MAZI 3 RÜZGAR ENERJİSİ SANTRALİ ELEKTRİK ÜRETİM A.Ş. [MAZI 3 WIND ENERGY PLANT ELECTRICITY GENERATION INC.]154 KV ( ~ 7 KM ) MAZI 3 WIND PLANT ETL06 05 200920 07 2009
877.165,50 $
485.926,00 TL
3
MODERN ENERJİ SAN.VE TİC.A.Ş. [MODERN Energy Industry and Trade Inc.]154 kV. DOUBLE CIRCUIT 795 MCM 6,215 km MODERN ENERGY SUBSTATION - ULAŞ SUBSTATION ETL  08.06.200627.02.2007
898.397,00 $
4
BOREAS ENERJİ ÜRETİM SİSTEMLERİ A.Ş. [BOREAS Energy Generation Systems Inc.]154 KV. 795 MCM BOREAS WPP SUBSTATION - ENEZ SUBSTATION ETL  30 04 200931 12 2009
561.442,40 €
5
MODERN ENERJİ SAN.VE TİC.A.Ş. [MODERN Energy Industry and Trade Inc.]154 Kv. 2 KM DOUBLE CIRCUIT 1272 mcm CONDUCTIVE ETL  BETWEEN ZETES SUBSTATION - YENİÇATALAĞZI SUBSTATION12 02 200830 06 2009
466.028,88 $
6
BARES Inc. - ANKARA154 kV. 3X477 MCM 8.060 km BANDIRMA WPP - BANDIRMA III SUBSTATION ETL  03 01 200514 03 2006
400.000,00 $
7
TEKTUĞ ELEKTRİK ÜR. A.Ş. [TEKTUĞ Electricity Gen. Inc.] [Subcontractor of ÇİLTUĞ Heat Industry and Trade Inc.]  154 kV. 10,604 km (KARGILIK HPP - ANDIRIN SUBSTATION) BRŞ.N. - KALEALTI HPP ETL  27.02.200631.10.2006
278.463,00 TL
8
AREVA T & D ENERJİ ENDÜSTRİSİ A.Ş. [AREVA T & D Energy Industry Inc.]154 KV. BÜYÜKÇEKMECE - SİLİVRİ BRŞ.N. - ÇATALCA WPP ETL  03 07 200716 05 2008
119.900,00 €
9
ŞURA MÜHENDİSLİK SAN.TİC.A.Ş. - GAZİANTEP [ŞURA Engineering Ind. Tra. Inc. in Gaziantep]154 kV. GAZİANTEP - BİRECİK ETL01.05.200631 05 2006
162.000,00 TL
10
S.S.BOĞAZİÇİ - ESENTEPE  KONUT YAPI KOOPERATİFİ - KAHRAMANMARAŞ [Limited Liability Boğaziçin Mass Housing Cooperative in Kahramanmaraş]154 KV. MENZELET HPP - NARLI ETL27 09 200531 03 2006
137.000,00 TL
11
Subcontractor of ÇİLTUĞ Heat Industry and Trade Inc.SINGLE CIRCUIT 3/0 NCN ETL BETWEEN KEBAN SWITCHING II SUBSTATION - KEBAN STREAM HPP 34,5 KV.  15.11.200615.03.2007
70.000,00 TL
12
BERGAMA RÜZGAR
ENERJİSİ SANTRALİ ENERJİ ÜRETİM A.Ş. [BERGAMA Wind Power Plant Energy Generation Inc.]
ETL BETWEEN 154 KV. 1272 MCM ( ~ 22 km ) BERGAMA WPP SUBSTATION AND VIKING SUBSTATION  17 08 200927 02 2010
1.141.151,46 $